5th July 2023,Mumbai: Ace Energy Infrastructure Pvt. Ltd. Has achieved a remarkable feat by successfully installing a 3600-meter pipeline of 24” diameter across the Subansiri River in Assam. This achievement, accomplished using the intersect method of Horizontal Directional Drilling (HDD), positions the company among the largest pipeline installations worldwide employing this technique. The project was undertaken for Indradhanush Gas Grid Limited (IGGL), a joint venture of prominent oil and gas companies in India, in collaboration with MECON Limited, India Ltd. Serving as the Project Management Consultant (PMC). The objective was to extend the Pradhan Mantri Urja Ganga (National Natural Gas Grid) to the North Eastern states of India, a visionary project initiated by the honorable Prime Minister of India and supported by the Ministry of Petroleum and Natural Gas.

Mr. Ravneet Singh, Director of Ace Energy Infrastructure Pvt. Ltd., expressed his satisfaction with this significant accomplishment. He emphasized the exceptional engineering talent and competencies displayed by infrastructure companies in India. The team of experts successfully overcame various technical and logistical challenges with precision and dedication, leading to the completion of this complex HDD crossing milestone.

Mr. Tarun Singh, another Director of Ace Energy Infrastructure Pvt. Ltd., highlighted the company’s experience in executing challenging projects and their unwavering commitment to quality. He stressed the importance of uniting expertise, passion, and determination to overcome any obstacle.

The CEO of Indradhanush Gas Grid Ltd., Mr. Ajit Kumar Thakur, acknowledged the monumental nature of this accomplishment. He recognized the collective efforts of Indradhanush Gas Grid Limited, MECON Ltd., and Ace Energy Infrastructure Pvt. Ltd. In realizing the country’s strategic vision of expanding access to cleaner energy by establishing natural gas infrastructure in the major demand centers of North East India.

What distinguishes this achievement even further are the extraordinary circumstances and challenges faced during the drilling process:

1. Extremely difficult site conditions: The location of both banks of the river presented extreme inaccessibility, situated in North Lakhimpur and Majuli Districts of Assam with no motorable roads. Access to the Majuli side was achieved by constructing a temporary coffer dam across the Lohit River, which was subsequently washed out due to flash floods. Furthermore, crossing the river itself was possible only through a rudimentary ferry that could barely accommodate cars. The task was further complicated by the narrow weather window during which equipment could be mobilized, as the entire area gets waterlogged between June and October.

2. Extensive job planning: The success of the project relied on meticulous planning, including methods, equipment, and manpower, several months in advance. Equipment such as tracking and guidance tools, recycling units, mud pumps, drill pipes, swivels, and various tooling, along with HDD rigs and sufficient redundancy, were procured well in advance and had to be mobilized to the remote project site.

3. Hard work and determination: The team at Ace Energy Infrastructure worked tirelessly day and night for the past five months without a single break, showcasing their unwavering commitment to the project’s success.

4. Perseverance and learning from setbacks: Despite facing adverse situations such as flash floods that washed away the only access to the site (the temporary coffer dam) and encountering drill string breakages, the team remained resolute in their pursuit of excellence.

5. Adaptability and incorporating ground-level feedback: Throughout the project execution, the team recognized the need to re-evaluate and re-engineer their plans based on the dynamics of the project site. Valuable insights from experienced personnel on the ground played a crucial role in improvising methods and ensuring continuous improvement.

Ace Energy Infrastructure Pvt. Ltd. Was founded in 2007 and has its headquarters in Mumbai. Over the years, the company has flourished through entrepreneurial leadership and the ability to overcome adversity, establishing a strong track record in executing diverse projects across the nation. With expertise and resources tailored for the energy, oil and gas, power, and petrochemical industries, Ace Energy Infrastructure is committed to building critical supply chains that fuel the growth of the nation.

The successful Installation of the 3600-meter pipeline across the Subansiri River underscores Ace Energy Infrastructure Pvt. Ltd.’s commitment to excellence, innovation, and the development of crucial infrastructure in India’s energy sector. This accomplishment will contribute significantly to expanding access to cleaner energy in the North Eastern states of the country, aligning with the government’s strategic vision for sustainable growth and development.